Friday, June 28, 2013

Proceeding Number A.12-04-019 ADMINISTRATIVE LAW JUDGE’S RULING RESETTING PREHEARING CONFERENCE DATE, CIRCULATING ERRATA SHEET AND EXTENDING SETTLEMENT SUBMISSION DATE

ABSTRACT:  Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, ADMINISTRATIVE LAW JUDGE’S RULING RESETTING PREHEARING CONFERENCE DATE, CIRCULATING ERRATA SHEET AND EXTENDING SETTLEMENT SUBMISSION DATE document, including ATTACHMENT A, is embedded. Importantly, IT IS RULED that
1. The Attachment A errata sheet hereby replaces page 7 of the May 30, 2013 Administrative Law Judge’s Ruling After Evidentiary Hearings.
2. The email ALJ ruling of June 11, 2013 that granted the joint request for an extension from June 14 to June 28, 2013 for the submission date of a settlement proposal for issues not related to groundwater replenishment is hereby memorialized but mooted by a new extension.
3. In response to the request of seventeen Parties and for good cause shown, and to memorialize my email ruling of June 25, 2013, the previously set June 28, 2013 date for submission of a settlement proposal is vacated and July 31, 2013 is the new submission date. It is unlikely that adequate grounds would be found to exist for any further extension of the settlement submission date.

Filing Date 06-28-13