ASSIGNED COMMISSIONER’S RULING, JOINED BY AN ADMINISTRATIVE LAW JUDGE, REAFFIRMING DENIAL OF JOINT MOTION OF SETTLING PARTIES
Saturday, June 14, 2014
Proceeding Number A.12-04-019 ASSIGNED COMMISSIONER’S RULING, JOINED BY AN ADMINISTRATIVE LAW JUDGE, REAFFIRMING DENIAL OF JOINT MOTION OF SETTLING PARTIES
ABSTRACT: Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, ASSIGNED COMMISSIONER’s RULING, JOINED BY AN ADMINISTRATIVE LAW JUDGE, REAFFIRMING DENIAL OF JOINT MOTION OF SETTLING PARTIES document is embedded. IT IS RULED that the request for reconsideration of their prior “Joint Motion to Reduce the Special Request 1 Surcharge” set forth in the “Settling Parties’ Joint Comments on Ruling Requesting Comments on Surcharge Options and Proposals” is denied. The previous denial of the Settling Parties’ Joint Motion to Reduce the Special Request 1 Surcharge is reaffirmed.
Filing Date 6-13-14
ASSIGNED COMMISSIONER’S RULING, JOINED BY AN ADMINISTRATIVE LAW JUDGE, REAFFIRMING DENIAL OF JOINT MOTION OF SETTLING PARTIES
ASSIGNED COMMISSIONER’S RULING, JOINED BY AN ADMINISTRATIVE LAW JUDGE, REAFFIRMING DENIAL OF JOINT MOTION OF SETTLING PARTIES
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment