CPCN Track
Certificate of Public Convenience and Necessity |
CEQA Track
California Environmental Quality Act |
||
No later than
January 30, 2015
|
DEIR circulated for
comment
|
||
15 days after
issuance of
DEIR (no later
than February
17, 2015)
|
Cal-Am to file and serve a common outline for legal and policy briefs, after consultation with parties
|
||
45 days after
issuance of DEIR
(no later than
March 16, 2015)
|
Comments on DEIR due
|
||
60 days after
issuance of
DEIR (no later
than April 1,
2015)
|
Common Outline
Opening Briefs
filed and served on
legal and policy
issues
|
||
75 days after
issuance of
DEIR (no later
than April 16,
2015)
|
Reply Briefs filed
and served on legal
and policy issues
|
||
July 2015
|
Phase 1 of the
Proceeding
submitted with the
publication of the
FEIR
|
July, 2015
(no later than
July 30, 2015)
|
FEIR published
|
3rd Quarter
2015
|
Phase 1
Proposed Decision
addressing
certification of FEIR
and issuance of
CPCN
|
||
3rd Quarter
2015
|
Target for
Commission Action
on Phase 1
Proposed Decision
|
Filing Date 8-21-14ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE