Proceeding Number A.12-04-019 ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE

ABSTRACT:  Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE document is embedded. The updated schedule is set forth below.

                        CPCN Track
Certificate of Public Convenience and Necessity
                       CEQA Track
California Environmental Quality Act


No later than
January 30, 2015
DEIR circulated for
comment
15 days after
issuance of
DEIR (no later
than February
17, 2015)
Cal-Am to file and serve a common outline for legal and policy briefs, after consultation with parties




45 days after
issuance of DEIR
(no later than
March 16, 2015)
Comments on DEIR due
60 days after
issuance of
DEIR (no later
than April 1,
2015)
Common Outline
Opening Briefs
filed and served on
legal and policy
issues


75 days after
issuance of
DEIR (no later
than April 16,
2015)
Reply Briefs filed
and served on legal
and policy issues


July 2015
Phase 1 of the
Proceeding
submitted with the
publication of the
FEIR
July, 2015
(no later than
July 30, 2015)
FEIR published
3rd Quarter
2015
Phase 1
Proposed Decision
addressing
certification of FEIR
and issuance of
CPCN


3rd Quarter
2015
Target for
Commission Action
on Phase 1
Proposed Decision



Importantly, “The CPUC Energy Division has encountered delays that we believe will make it impossible for us to meet the scheduled 3rd quarter 2014 publication date for the Monterey Peninsula Water Supply Project (MPWSP) Draft Environmental Impact Report (EIR).  Energy Division accordingly requests a four-month extension of the schedule to allow the MPWSP EIR team to complete the necessary analyses and adequately address the technical issues surrounding the project. With the extension, publication of the MPWSP Draft EIR would occur in January 2015 and certification of the Final EIR in July 2015.”