Friday, September 08, 2006
CHRONOLOGY of Ocean Avenue Medians Renovation Project: STEPS 2-5
George DiPeso Landscaping Tree Stump Removal Machine
Location: Ocean Avenue Median between Dolores St. & San Carlos St.
UPDATE:
STEP 2: Tree Stump Removal: Weeks of September 4-8 and 11-15, 2006
STEP 3: Irrigation System Installation; Weeks of September 18-22 and 25-29, 2006.
STEP 4: Landscape with drought tolerant plants: Week of October 2-6, 2006.
STEP 5: Lighting Installation (subject to City Council approval).
Note: Dates approximate
Sources: George DiPeso, Designer & Contractor, George DiPeso Landscaping, 1497 Highland Pl., Seaside, 394-4664, since 1977. An award-winning residential, commercial and city park landscape designer; & empirical observation.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment