Proceeding Number A.12-04-019 ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE FOR PHASE 2

ABSTRACT:  Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE FOR PHASE 2 document is embedded. Phase 2 Schedule (Revised), as follows:
November 6, 2015: Phase 2 (GWR decision phase) commences with testimony of interested parties
November and December 2015: Settlement discussions
December 18, 2015: Concurrent Rebuttal Testimony
January 2016: Evidentiary Hearings
February 2016: Briefing
May 2016: Target for Phase 2 Proposed Decision
June 2016: Target for Commission action on Phase 2 Decision