Thursday, May 16, 2019

GOVERNANCE COMMITTEE FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT AGENDA & MINUTES, May 15, 2019


GOVERNANCE COMMITTEE FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT
California American Water  Monterey County Board of Supervisors
Monterey Peninsula Regional Water Authority  Monterey Peninsula Water Management District
REGULAR MEETING
Monterey Peninsula Water Supply Project
Governance Committee
***************
Wednesday, May 15, 2019, 2:00 PM

Saturday, August 23, 2014

Friday, May 16, 2014

Board of Directors, Monterey Peninsula Water Management District, Regular Meeting Agenda, May 19, 2014, Featuring Agenda Items CONSENT CALENDAR 6. CONSIDER APPROVAL OF AMENDMENT TO AMENDED AND RESTATED AGREEMENT TO FORM THE MONEREY PENINSULA WATER SUPPLY GOVERNANCE COMMITTEE and GENERAL MANAGER’S REPORT 13. UPDATE ON DEVELOPMENT OF WATER SUPPLY PROJECTS

ABSTRACT:  The Board of Directors, Monterey Peninsula Water Management District, Regular Meeting Agenda, Monday, May 19, 2014 is embedded.  Agenda Items CONSENT CALENDAR 6. CONSIDER APPROVAL OF AMENDMENT TO AMENDED AND RESTATED AGREEMENT TO FORM THE MONEREY PENINSULA WATER SUPPLY GOVERNANCE COMMITTEE and GENERAL MANAGER’S REPORT 13. UPDATE ON DEVELOPMENT OF WATER SUPPLY PROJECTS are featured.
AGENDA
Regular Meeting
Board of Directors
Monterey Peninsula Water Management District
******************
Monday, May 19, 2014, 7:00 pm

Conference Room, Monterey Peninsula Water Management District

5 Harris Court, Building G, Monterey, CA



ITEM:
CONSENT CALENDAR

6.
CONSIDER APPROVAL OF AMENDMENT TO AMENDED AND RESTATED AGREEMENT TO FORM THE MONEREY PENINSULA WATER SUPPLY GOVERNANCE COMMITTEE

Meeting Date:
May 19, 2014
Budgeted: 
Yes

From:
David J. Stoldt
Program/
N/A

General Manager
Line Item No.:    

Prepared By:
David J. Stoldt
Cost Estimate:


General Counsel Approval:  N/A
Committee Recommendation:  The Administrative Committee considered this item on May 12, 2014 and recommended approval.
CEQA Compliance:  N/A

SUMMARY:  The revision under consideration was requested by the Governance Committee at its meeting of April 16, 2014. The Governance Committee also requested that the Water Authority and/or the Water Management District undertake the preparation and advertisement of an RFP and Scope of Work for a VE Consultant, and to make a recommendation for selection following a review of proposals received. Since time was of the essence, the Water Authority accepted the task, and the RFP has now been sent out to potential consultants.

The Governance Committee will make the final selection and the Water Authority will then award and administer the contract.

RECOMMENDATION:  The General Manager recommends that the Administrative Committee recommend the Board of Directors approve the amendment.

EXHIBIT
6-A      Proposed Amendment                               

RE: GENERAL MANAGER’S REPORT
13.

ITEM:
GENERAL MANAGER’S REPORT

13.
UPDATE ON DEVELOPMENT OF WATER SUPPLY PROJECTS

Meeting Date:
May 19, 2014
Budgeted: 
N/A

From:
David J. Stoldt
Program/
N/A

General Manager
Line Item No.:     N/A

Prepared By:
David J. Stoldt
Cost Estimate:
N/A

General Counsel Approval:  N/A
Committee Recommendation:  N/A
CEQA Compliance:  N/A

DISCUSSION:

SWRCB:  The District General Manager, General Counsel, Water Demand Manager, and District Engineer met with enforcement staff of the State Water Resources Control Board, Cal-Am, the Regional Water Authority, Sierra Club, attorney for water rights holders, and the Pebble Beach Company (Parties to the lawsuit over the Cease and Desist Order (CDO)) and held initial discussions about the process for petitioning for a modification of the CDO under section 1832 of the California Water Code.  A confidential proposed set of terms and conditions for an extension of the CDO was prepared and forwarded to the SWRCB the third week of April.

Desalination Facility (A.12-04-019):  Legislation was for the Water Rate Relief Bonds (SB 936) was unanimously passed by the Senate Governance and Finance Committee on April 2nd and the Senate Energy, Utilities, and Communications Committee on April 29th.

Pure Water Monterey - Groundwater Replenishment Project (GWR):  District staff has been meeting with MRWPCA staff and consultants every other Friday, tracking project progress. CEQA work and source water feasibility studies continue to proceed.

District staff have been working jointly with MRWPCA staff to develop business terms and conditions for source water agreements. 

The District received three statements of qualifications for the study of externalities related to the Pure Water Monterey project – See agenda item 19.

The draft Water Purchase Agreement is being researched and expected to be summarized in a term sheet shortly after source water terms and conditions are agreed upon.

A preliminary budget for GWR has been recommended and is included in this meeting agenda under item 20.

Aquifer Storage and Recovery (ASR):  The District is in negotiation with the City of Seaside over the future easement for the Santa Margarita site.

Alternative Desalination Project:  On April 17th the General Manager met with Grant Gordon the Chief Operating Officer of DeepWater Desal.  The General Manager will provide an oral update at the May 19 Board meeting.

Local Water Projects:  The District is continuing to fund a portion of the City of Pacific Grove project, the Airport District project, and has entered into discussions with the Pebble Beach Company for an alternative supply for Del Monte Golf Course and with the Fairgrounds concerning the use of non-potable supplies for bathroom use.

MPWSP Governance Committee:  The Governance Committee has assigned the role of procuring a value engineering consultant to the public agencies.  Consent Calendar item 6 relates to such action.  The District is jointly working with the Water Authority to secure a Value Engineer for the desalination project.  The District Engineer participated in a review and selection panel on May 15th.

Monterey Peninsula Regional Water Authority:  The General Manager presented an update on the DeepWater Desal project to the Authority at its May 8th meeting.

Other:  The General Manager participated in a Water Forum sponsored by the City of Marina on April 29th, was a panelist on the State Water Bond topic for the local California League of Cities meeting May 12th, and has been participating in a new group titled the Del Monte Forest Partners in Water Strategies to help identify additional supplies to the Reclamation Project.

The Association of California Water Agencies (ACWA) conference was hosted in Monterey.  The District and MRWPCA hosted a tour of the GWR pilot plant followed by a reception at the Wharf Marketplace.

EXHIBITS

None

Friday, January 10, 2014

DESIGN-BUILD AGREEMENT FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT DESALINATION INFRASTRUCTURE between CALIFORNIA-AMERICAN WATER COMPANY and CDM CONSTRUCTORS INC.

ABSTRACT: The DESIGN-BUILD AGREEMENT FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT DESALINATION INFRASTRUCTURE between CALIFORNIA-AMERICAN WATER COMPANY and CDM CONSTRUCTORS INC. document, Dated as of December 18, 2013, is embedded. Links to the document, CDM Constructors, Inc. Drawings for Proposal, Propoasl and Technical Proposal are provided. 

CAW CDM Smith DB SWRO Full Agreement With Redacted DrawingsDESIGN-BUILD AGREEMENT FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT DESALINATION INFRASTRUCTURE between CALIFORNIA-AMERICAN WATER COMPANY and CDM CONSTRUCTORS INC.
Dated as of December 18, 2013


Monday, July 08, 2013

GOVERNANCE COMMITTEE FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT AGENDA & MINUTES July 11, 2013

AGENDA, REGULAR MEETING
GOVERNANCE COMMITTEE FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT
July 11, 2013


Action Items - Public Comment will be Received

 

 

2.

Consider Request that Governance Committee Meetings be Recorded and Televised

 

 



Monday, May 20, 2013

Governance Committee for the Monterey Peninsula Water Supply Project AGENDA & MINUTES REGULAR MEETING, May 23, 2013

ABSTRACT:  The Governance Committee for the Monterey Peninsula Water Supply Project is scheduled to consider Agenda Items, namely Adopt Minutes of April 22 and May 17, 2013 Committee Meetings, Review and Comment on Draft Design Build Request for Proposals Prepared by California-American Water, Status Report on Development of Term Sheet for Power Sales Agreement with Monterey Regional Waste Management District for Use of Landfill Gas Generated Electricity for the Proposed Desalination Plant and Discussion of Items to be Placed on Future Agendas, at the Thursday, May 23, 2013 meeting.


Governance Committee
FOR THE
Monterey Peninsula Water Supply Project

California American Water Ÿ Monterey County Board of Supervisors
Monterey Peninsula Regional Water Authority Ÿ Monterey Peninsula Water Management District

REGULAR MEETING
Governance Committee for the
Monterey Peninsula Water Supply Project
***************
Thursday, May 23, 2013, 1 PM
Monterey Peninsula Water Management District, Conference Room,
5 Harris Court, Building G., Monterey, CA

Governance Committee Members:
California American Water
Robert MacLean

Monterey Peninsula Regional Water Authority
Jason Burnett,
Alt.-  Chuck Della Sala

County of Monterey
David Potter
Alt. - Simon Salinas

Monterey Peninsula Water Management District
Bob Brower
Alt. – Jeanne Byrne

Staff Contact:
David J. Stoldt, MPWMD
Arlene Tavani, MPWMD


Call to Order/Roll Call

Pledge of Allegiance

Public Comments
Anyone wishing to address the Committee on matters not listed on the agenda that are within the subject jurisdiction of the Committee, may do so during Public Comments. The public may comment on any other items listed on the agenda at the time they are considered by the Committee. Please limit your comment to 3 (three) minutes.

Agenda Items

1. Adopt Minutes of April 22 and May 17, 2013 Committee Meetings 

2. Review and Comment on Draft Design Build Request for Proposals Prepared by California-American Water


Attached as Exhibits 2-A through 2-D are documents submitted by California American Water for committee review and discussion.

 

Exhibit 2-A: Cal-Am Notification #2 – Draft Desalination Infrastructure Request for Proposals and Draft Design-Build Contract to be Issued by California American Water
 

Exhibit 2-B: Request for Proposals – Design and Construction of Desalination Infrastructure for the Monterey Peninsula Water Supply Project
 

Exhibit 2-C: RFP Issuance Draft – Design-Build Agreement for the Monterey Peninsula Water Supply Project Desalination Infrastructure
 

Exhibit 2-D: Appendices to Draft-Design-Build Agreement for the Monterey Peninsula Water Supply Project Desalination Infrastructure 

3. Status Report on Development of Term Sheet for Power Sales Agreement with Monterey Regional Waste Management District for Use of Landfill Gas Generated Electricity for the Proposed Desalination Plant

4. Discussion of Items to be Placed on Future Agendas

Adjournment



FINAL MINUTES, Regular Meeting
Governance Committee for the Monterey Peninsula Water Supply Project
May 23, 2013

Wednesday, May 15, 2013

Governance Committee for the Monterey Peninsula Water Supply Project AGENDA SPECIAL MEETING & MINUTES 17 May 2013

ABSTRACT:  The Governance Committee for the Monterey Peninsula Water Supply Project is scheduled to consider Agenda Items, namely Develop Draft Criteria for Groundwater Replenishment Project Recommendation for June 12, 2013 California Public Utilities Commission Workshop, Receive Presentation by Cal-Poly Architectural Design Team on Preliminary Concepts and Provide Feedback and Direction for Further Development and Discussion of Items to be Placed on Future Agendas, at the Friday, May 17, 2013 Special Meeting.

Governance Committee
for the
Monterey Peninsula Water Supply Project

California American Water  Monterey County Board of Supervisors 
Monterey Peninsula Regional Water Authority  Monterey Peninsula Water Management District

SPECIAL MEETING
Monterey Peninsula Water Supply Project
Governance Committee
***************
Friday, May 17, 2013, 1 PM
Monterey Peninsula Water Management District, Conference Room,
5 Harris Court, Building G., Monterey, CA

Governance Committee Members:
California American Water
Robert MacLean

Monterey Peninsula Regional Water Authority
Jason Burnett,
Alt.-  Chuck Della Sala

County of Monterey
David Potter
Alt. - Simon Salinas

Monterey Peninsula Water Management District
Bob Brower
Alt. – Jeanne Byrne

Staff Contact:
David J. Stoldt, MPWMD
Arlene Tavani, MPWMD
  

Call to Order/Roll Call

Pledge of Allegiance

Public Comments
Anyone wishing to address the Committee on matters not listed on the agenda that are within the subject jurisdiction of the Committee, may do so during Public Comments. The public may comment on any other items listed on the agenda at the time they are considered by the Committee. Please limit your comment to 3 (three) minutes.

Agenda Items

1. Develop Draft Criteria for Groundwater Replenishment Project Recommendation for June 12, 2013 California Public Utilities Commission Workshop 

2. Receive Presentation by Cal-Poly Architectural Design Team on Preliminary Concepts and Provide Feedback and Direction for Further Development

3. Discussion of Items to be Placed on Future Agendas

Adjournment



DRAFT MINUTES
GOVERNANCE COMMITTEE FOR THE MONTEREY PENINSULA WATER SUPPLY PROJECT
May 17, 2013

Tuesday, March 19, 2013

Governance Committee for the Monterey Peninsula Water Supply Project AGENDA & MINUTES 20 March 2013

ABSTRACT: The Monterey Peninsula Water Supply Project Governance Committee is scheduled to consider Agenda Items, namely Review and Provide Recommendations for Design Build Request for Qualifications Prepared by California-American Water and Develop Plan for Coordination with Architectural Design Team, at the Wednesday, March 20, 2013 meeting. A link to the AGENDA is provided; featured agenda items are reproduced and Attachment 1 – Cal-Am Notification #1 and Attachment 2 – Draft RFQ documents are embedded for Agenda Item 2. Review and Provide Recommendations for Design Build Request for Qualifications Prepared by California-American Water.

REGULAR MEETING
Monterey Peninsula Water Supply Project
Governance Committee

***************

Wednesday, March 20, 2013, 4:00 PM
Monterey Peninsula Water Management District, Conference Room,
5 Harris Court, Building G., Monterey, CA

Governance Committee Members:

California American Water
Robert MacLean

Monterey Peninsula Regional Water Authority
Jason Burnett,
Alt.- Chuck Della Sala
County of Monterey

David Potter
Alt. - Simon Salinas

Monterey Peninsula Water Management District
Bob Brower, Interim Representative

Staff Contact:
David J. Stoldt, MPWMD
Arlene Tavani, MPWMD


Call to Order/Roll Call


Agenda Items



2. Review and Provide Recommendations for Design Build Request for Qualifications Prepared by California-American Water (Recommendation under Category B1 of Governance Agreement)


Attachment 1 -- Cal-Am Notification #1


Attachment 2 -- Draft RFQ

3. Develop Plan for Coordination with Architectural Design Team (Recommendation under Category B5 of Governance Agreement)


Governance Committee 

for the 
Monterey Peninsula Water Supply Project 

California American Water  Monterey County Board of Supervisors 

Monterey Peninsula Regional Water Authority  Monterey Peninsula Water Management District 

Monterey Peninsula Water Supply Project 
Governance Committee 
March 20, 2013

Call to Order: The meeting was called to order at 4:00 pm in the MPWMD conference room.

Members present: Robert MacLean, California-American Water (Cal-Am)
Jason Burnett, Monterey Peninsula Regional Water Authority (MPRWA)
David Potter, County of Monterey (County)
Jeanne Byrne, (Alternate) Monterey Peninsula Water Management District (MPWMD)

Pledge of Allegiance: The assembly recited the Pledge of Allegiance

Public Comments: No comments were directed to the committee.

Agenda Items

The Chair received public comment on each agenda item.

1. Approve Minutes of March 13, 2013 Committee Meeting and Provide Direction on Format for Subsequent Reports

On a motion by Potter and second of Byrne, the minutes were adopted on a vote of 3 – 0 by Burnett, Byrne and Potter.

2. Review and Provide Recommendation for Design Build Request for Qualifications Prepared by California-American Water (Recommendation under Category B1 of Governance Agreement)

Anthony J. Cerasuolo, Vice President, Legal – Operations for California American Water, provided a brief overview of the Request for Qualifications (RFQ) and stated that it would be issued to interested parties on April 1, 2013. On May 31, 2013 Cal-Am will issue a list of firms chosen to receive a Request for Proposals (RFP). On November 15, 2013 an agreement with the selected firm should be executed. Cerasuolo responded to questions and comments from the committee and members of the audience. In response to the comments received, a list ofproposed amendments to the RFQ was developed.

On a motion by Potter and second of Byrne, the RFQ was approved with the following amendments on a vote of 3 – 0 by Burnett, Byrne and Potter.

· Page 7, section 3.3.3 - Include in the discussion of Power Supply a reference to utilization of alternative power sources such as landfill gas.

· Page 9 - specify that the SOQ shall be limited to 15, double-sided pages.

· Page 9 – Specify that prospective Design-Build Entities shall have no contact with the Monterey Peninsula Regional Water Authority Technical Advisory Committee. Contact with permitting agencies strictly related to questions about permitting issues will be allowed. Kris Helms Consulting and Separation Processes, Inc. will be considered ineligible firms.

· Pages 18 and 19 – Include a reference to compliance with environmental laws.

· Pages 18 and 19 – Include a reference to compliance with prevailing wage and other labor laws such as diversity of workforce. Under Selection Criteria add a bullet, “local hiring experience”.

· Page 18 - Include a question that asks about the Design-Build Entity’s experience in designing plants that are cost effective to maintain and highly adaptable to new technologies over time.

· Remove any reference to Leed Certification. Focus should be on “sustainable green design” that will result in a savings to the ratepayer.

· Add a question regarding the number of change orders on past projects that were initiated by the Design-Build Entity as opposed to owner initiated.

· Ask about the Design-Build Entity’s history of responsiveness to the owner, after a project is complete.

· Insure that formatting of document is consistent, i.e. headings and fonts.

During the discussion, concerns were expressed about bonding requirements for subcontractors. MacLean stated that the bonding guarantee is from the design-builder or engineer, whichever entity is specified as the prime contractor. That entity will guarantee completion of the project and be responsible for performance of the contractors. It may be appropriate to discuss subcontractor bonding requirements when the RFP is developed.

3. Develop Plan for Coordination with Architectural Design Team (Recommendation under Category B5 of Governance Agreement)

John Kilpatrick, Engineering Manager – Project Delivery for California American Water, reviewed the schedule for development, review and selection of a final design for facilities that will be located at the desal plant site. The committee discussed how to best provide guidance to the design team and the opportunity for public review of the design concepts. Byrne offered to participate in the review effort. It was suggested that in May, the design team meet in Monterey with the committee to present their conceptual drawings. In June, the team could meet again in Monterey to present the one concept selected for development. In August, another review of the final design would occur in Monterey for committee review, before it is distributed with the RFP. At the April Governance Committee meeting, Cal-Am will present a final architectural design review/completion schedule.

4. Discussion of Items to be Placed for Future Agendas

April - present schedule for Cal-Poly architectural design team review; action needed based on response from CPUC on request to conduct workshop on GWR; and presentation from William Merry of Monterey Regional Waste Management District on landfill gas as an alternative energy source for desal. May – discuss development of request for proposals for design build entity.

5. Schedule Next Meeting Date

The meeting was scheduled for Wednesday, April 17, 2013 at 2 pm.

Adjournment

The meeting adjourned at 5:20 pm.

Monday, March 18, 2013

Water Supply Planning Committee of the Monterey Peninsula Water Management District AGENDA ITEMS DEVELOP RECOMMENDATION TO THE BOARD RE APPOINTMENT OF A REPRESENTATIVE TO THE MONTEREY PENINSULA WATER SUPPLY PROJECT GOVERNANCE COMMITTEE & PROGRESS REPORT ON INVESTIGATION INTO DESALINATION CONTINGENCY PROJECT, March 11, 2013

ABSTRACT:  The Water Supply Planning Committee of the Monterey Peninsula Water Management District considered two agenda items, namely DEVELOP RECOMMENDATION TO THE BOARD RE APPOINTMENT OF A REPRESENTATIVE TO THE MONTEREY PENINSULA WATER SUPPLY PROJECT GOVERNANCE COMMITTEE & PROGRESS REPORT ON INVESTIGATION INTO DESALINATION CONTINGENCY PROJECT, at the March 11, 2013 meeting.  Exhibit 2-A (Final Agreement to Form the Monterey Peninsula Water Supply Project Governance Committee) and Progress Report on Investigation into Desalination Contingency Project agenda item document submitted by MPWMD and document submitted by Harvey Billig are embedded.


Water Supply Planning Committee
Of the Monterey Peninsula Water Management District
*********
Monday, March 11 2013, 9 am
District Conference Room, 5 Harris Court, Building G, Monterey, CA

Water Supply Planning Committee Members:
Robert S. Brower, Sr. Chair
Jeanne Byrne
David Pendergrass

Alternate:
Kristi Markey

Staff Contact
David J. Stoldt,
General Manager


Call to Order

Action Items – Public comment will be received on all Action Items


WATER SUPPLY PLANNING COMMITTEE

ITEM:
ACTION ITEMS

2.
DEVELOP RECOMMENDATION TO THE BOARD RE APPOINTMENT OF A REPRESENTATIVE TO THE MONTEREY PENINSULA WATER SUPPLY PROJECT GOVERNANCE COMMITTEE

Meeting Date:
March 11, 2013

 

 


From:
David J. Stoldt,



General Manager




Prepared By:
Arlene Tavani









SUMMARY:   Attached as Exhibit 2-A is the final Agreement to Form the Monterey Peninsula Water Supply Project Governance Committee.  The committee will refer to the agreement in its discussion of MPWMD representation on the Governance Committee.

RECOMMENDATION:  The Committee should develop a recommendation re representation on the Governance Committee.

EXHIBITS
2-A    Final Agreement to Form the Monterey Peninsula Water Supply Project Governance Committee
  
 

EXHIBIT
2-A  Final Agreement to Form the Monterey Peninsula Water Supply Project Governance Committee
  

Discussion Items – Public comment will be received on all Discussion Items

5. Progress Report on Investigation into Desalination Contingency Project
(Documents for review to be submitted at the meeting.)
Ø       Document submitted by MPWMD