Saturday, November 10, 2012

EXECUTIVE SUMMARY HIGHLIGHTS: Evaluation of Seawater Desalination Projects, November 2012, DRAFT REPORT, Separation Processes, Inc. (SPI)

ABSRACT: EXECUTIVE SUMMARY HIGHLIGHTS from the DRAFT REPORT Evaluation of Seawater Desalination Projects, November 2012, prepared by Separation Processes, Inc. (SPI) for Monterey Peninsula Regional Water Authority are presented. The DRAFT REPORT evaluated CALIFORNIA AMERICAN WATER (CAL-AM) DEEPWATER DESAL (DWD) and PEOPLES MOSS LANDING (PML) projects. Focusing on ECONOMICS and IMPLEMENTATION CONSIDERATIONS, as follows: “Overall, the final water production costs are fairly equivalent given the overall accuracy of the estimate and degree of project development.” 
Capital and Operating Cost Estimates
CAPITAL COSTS (in Millions 2012 Dollars)
TOTAL
California-American Water            DeepWater Desal             People’s
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$207
$175
$160
$134
$190
$161

ANNUAL O&M COSTS (in Millions 2012 Dollars)
TOTAL
California-American Water            DeepWater Desal             People’s        
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$11.0
$7.77
$12.3
$9.38
$10.1
$7.06

ANNUAL COST OF WATER (in Millions 2012 Dollars)
Production Cost of Water ($/AF)
California-American Water            DeepWater Desal             People’s 
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$2,555
$3,250
$2,385
$3,120
$2,345
$2,980

Desal Plant Startup:
Projected Cal-Am Project Implementation Schedule Quarters 3/4 2017
Projected DWD Project Implementation Schedule Quarters 2/3 2018
Projected PML Project Implementation Schedule Q 2/3 2019

Note: The Technical Advisory Committee of the Monterey Peninsula Regional Water Authority is scheduled to “receive an discuss” Separation Processes, Inc.’s report “Evaluation of Seawater Desalination Projects” at a Special Meeting on Tuesday, November 13, 2012 at 1:00 P.M. at Council Chamber, Few Memorial Hall of Records, Monterey, CA.


HIGHLIGHTS OF EXECUTIVE SUMMARY 

EXECUTIVE SUMMARY

Separation Processes Inc. (SPI) in association with Kris Helm Consulting (KHC) is providing engineering and consulting support to the Monterey Peninsula Regional Water Authority (MPWRA) to assist with the evaluation of three candidate desalination projects on the Monterey Peninsula. This report presents the results of our evaluation of the projects, targeted at replacing supplies currently extracted from the Carmel River but subject to a 1995 order from the State Water Resources Control board to secure an alternate source of supply by December, 2016.

The proposed strategy for meeting the projected annual demand within the California American Water service area of 15,250 acre-feet is a multi-pronged approach including permitted extractions from the Carmel River and Seaside Basin, an aquifer-storage and recovery system, and the existing Sand City desalination plant--totaling 6,250 acre-feet; leaving a 9,000 acre-feet gap in supply. Two alternatives are under consideration to compose this final supply—a 9,000 acre-feet production seawater desalination plant; or a 5,500 acre-feet seawater desalination plant in concert with a groundwater water replenishment project using advanced treated recycled water of 3,500 acre-feet.

This report presents the results of our evaluation of three candidate alternatives for the seawater desalination component of the overall water supply portfolio. California American Water is actively engaged with the California Public Utilities Commission to build a facility and secure the required supply. Two other development groups have proposed alternative projects for consideration—DeepWater Desal, LLC and the People’s Moss Landing Water Desal Project. The three projects were analyzed on functional, performance, economic and implementation grounds in an effort to provide a balanced evaluation for consideration by the MPRWA.

PROJECT SUMMARIES
The three projects are in the conceptual or preliminary stage of development and all three have as their objective to provide California American Water the seawater desal component of the required replacement water supply under State Water Resources Control Board Order No. 95-10.

Project Name Monterey Peninsula Water Supply Project (MPWSP) 

Proponent(s) California American Water (Cal-Am)

Location 46-acre site of vacant, disturbed land west of the MRWPCA Regional Treatment Plant (RTP).

Purpose To supply supplemental desal component of the Monterey Peninsula regional water supply

This project is currently under consideration by the California Public Utilities Commission (CPUC).

Production Volume 5.4 mgd or 9.0 mgd

Project Name DeepWater Desal (DWD) 

Proponent(s) DeepWater Desal, LLC, Dynegy Moss Landing Power Plant, MFJK Partnership of the Capurro Ranch, PV2 Solar, and Ecomert Technologies

Location Capurro Ranch Property, north of /Elkhorn Slough

Purpose Phase 1 to supply supplemental desal component of the Monterey Peninsula regional water supply

Phase 2 to supply northern customers

Production Volume Phase 1: 4.9 mgd or 9.1 mgd Phase 2: 22.0 mgd


Project Name The People’s Moss Landing Water Desal Project (PML) 

Proponent(s) DeSal America, LLC composed of Moss Landing Commercial Park, LLC; and Stanley and Patricia-Vance Lueck

Location Moss Landing Commercial Park

Purpose To supply supplemental desal component of the Monterey Peninsula regional water supply

This project is currently proposed as alternative to the Cal-Am MPWSP.

Production Volume 4.8 mgd or 9.4 mgd

PROJECT FUNCTION
We evaluated the function of each project in terms of project purpose, customers identified, adequacy of treatment approach, residuals handling, feed water characterization, quality of project information, and any omissions or fatal flaws in the information provided.

All three projects have available sites for building the required treatment facilities; and credible seawater intake and brine disposal approaches, though there are substantive differences among them. Cal-Am proposes to use a group of subsurface slant intake wells (up to eight for the maximum capacity plant alternative); DWD proposes a new screened open ocean intake installed at roughly 60-ft of depth; and PML is considering options to use either an existing seawater intake pump station drawing from the Moss Landing Harbor, or potentially a new screened open ocean intake installed coincident with an existing 51-in diameter concrete outfall pipeline owned by the Moss Landing Commercial Park.

Cal-Am and PML propose to serve only the identified demand within the Cal-Am service area at the two plant capacity increments under consideration; while DWD envisions a higher capacity regional project, capable of producing up to 25,000 AFY.

In terms of treatment approach—all three candidate teams propose to use reverse osmosis (RO) as the primary desalination technology. However, both DWD and PML propose a single pass RO system; while Cal-Am has proposed a partial double or two pass system—treating a portion of the product water from the first pass RO system with a second RO system and blending the supplies to form the final treated water. The issue relates to the quality of product water produced, more than treatment function; as either approach is considered functional.

Cal-Am and DWD will require offsite pipelines for feed, product water and brine disposal; while PML proposes to use existing intake and outfall pipelines originating on site; requiring only a product water delivery pipeline.

PROJECT PERFORMANCE
Performance of each proposed system was gauged relative to categories of plant design capacity, targeted product water quality and disinfection strategy.

For plant capacity, we considered the proposed instantaneous design capacity of each treatment facility in comparison to the required annual production increment—either 5,500 AFY or 9,000 AFY. What we found were wide variations—with Cal-Am proposing capacities of 5.4 mgd and 9.0 mgd; DWD of 4.9 mgd and 9.1 mgd; and PML at 4.8 mgd and 9.4 mgd.

The product quality produced by the proposed systems would differ based on the configuration of their proposed RO systems. Cal-Am’s proposed partial two-pass system could likely achieve chloride, boron, and total dissolved solids (TDS) consistent with current Carmel River supplies; but the single pass systems would not. We consider a lower salinity product supply an asset and evaluated all three projects (from an economic perspective) as having partial two-pass RO systems.

ECONOMICS
Capital and Operating Cost Estimates

CAPITAL COSTS (in Millions 2012 Dollars)
TOTAL
California-American Water            DeepWater Desal             People’s
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$207
$175
$160
$134
$190
$161

ANNUAL O&M COSTS (in Millions 2012 Dollars)
TOTAL
California-American Water            DeepWater Desal             People’s
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$11.0
$7.77
$12.3
$9.38
$10.1
$7.06

ANNUAL COST OF WATER (in Millions 2012 Dollars)
Production Cost of Water ($/AF)
California-American Water            DeepWater Desal             People’s
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
9 kAFY
5.5 kAFY
$2,555
$3,250
$2,385
$3,120
$2,345
$2,980

Overall, the final water production costs are fairly equivalent given the overall accuracy of the estimate and degree of project development. Cal-Am’s capital cost is the highest; owing largely to its high intake system cost. PML is proposing to reuse existing intake infrastructure; while DWD has an unspecified separate business entity which will be funding its intake, outside of the assigned DWD facility budget. Cal-Am’s operating cost is also relatively high, owing in large measure to higher stipulated energy costs than either DWD or PML—roughly $0.13/kW-hr vs. $0.08 kW-hr.

IMPLEMENTATION CONSIDERATIONS
The three projects are at varying states of development in terms of the regulatory permitting process. Cal-Am is further along than either DWD or PML, though DWD has completed or is nearing completion of their initial CEQA compliance documents.

Desal Plant Startup
Projected Cal-Am Project Implementation Schedule Quarters 3/4 2017
Projected DWD Project Implementation Schedule Quarters 2/3 2018
Projected PML Project Implementation Schedule Q 2/3 2019

Evaluation of Seawater Desalination Projects
DRAFT REPORT, November 2012
Prepared by: Separation Processes, Inc

Wednesday, November 07, 2012

APPROVED: Measure D - City of Carmel-By-The-Sea

COUNTY OF MONTEREY 
PRESIDENTIAL GENERAL ELECTION 
November 6, 2012
Semi-Final Official Report 6 (next report Friday Nov. 9, 2012)

Measure D - City of Carmel-By-The-Sea
2/2 100.00%


Vote Count
Percent
YES
1,333
75.40%
NO
435
24.60%
Total
1,768
100.00%


CARMEL-BY-THE-SEA 
TRANSACTION AND USE TAX (50% + 1/Majority Voter Approval Required)

“Shall Carmel-by-the-Sea increase transaction and use tax (sales tax) by 1% for 10 years, with an annual independent audit, to maintain essential services including fire, ambulance and police response times; fund capital needs including streets, beach, parks, forest and trails; increase code compliance; maintain libraries, Sunset Center and other public facilities; address CalPERS pension liabilities and other debt; and provide other general City services?”

Tuesday, November 06, 2012

TECHNICAL ADVISORY COMMITTEE (TAC) SPECIAL MEETING OF THE MONTEREY PENINSULA REGIONAL WATER AUTHORITY (MPRWA) AGENDA & MINUTES November 13, 2012

Mprwa Tac Special Meeting 11-13-12
SPECIAL MEETING AGENDA PACKET
TECHNICAL ADVISORY COMMITTEE, MONTEREY PENINSULA REGIONAL WATER AUTHORITY
November 13, 2012
Includes: Evaluation of Seawater Desalination Projects
November 2012
DRAFT REPORT
Prepared by:
Separation Processes, Inc.
3156 Lionshead Ave
Suite 2
Carlsbad, CA 92010

Note: Three projects, namely CALIFORNIA AMERICAN WATER (CAL-AM),.DEEPWATER DESAL (DWD) and PEOPLES MOSS LANDING (PML) were analyzed on functional, performance, economic and implementation grounds in an effort to provide a balanced evaluation for consideration by the MPRWA.
TECHNICAL ADVISORY COMMITTEE (TAC) MEMORANDUM WITH ATTACHMENTS
November 14, 2012
Report to MPRWA-TAC Financial Analysis of SPI Cost Comparison


DRAFT MINUTES, SPECIAL MEETING
TECHNICAL ADVISORY COMMITTEE, MONTEREY PENINSULA REGIONAL WATER AUTHORITY
November 13, 2012

Proceeding Number A.12-04-019 CALIFORNIA-AMERICAN WATER COMPANY CONTINGENCY PLAN COMPLIANCE FILING

RELATED NEWS ARTICLE: 
Cal Am files opposition with PUC to public ownership of desal plant 
Company tells PUC it could consider sharing oversight
By JIM JOHNSON Herald Staff Writer, 11/10/2012

EXCERPT HIGHLIGHTS:
In a separate filing, Cal Am outlined its contingency plans in case aspects of the desal project need to be changed. The filing includes backup plans for the desal plant's brackish source water, the plant site, plant failure or interruption, brine outfall, reduced demand forecasts and a project delay.
Among the contingency plans, Cal Am suggested the use of shallower slant wells or horizontal Ranney wells extracting from the Sand Dunes aquifer, an open ocean intake nearby, or a slant well or ocean open intake near Moss Landing Harbor using the old Refractories infrastructure owned by Nader Agha. Cal Am also suggested it could consider locating the desal plant in Moss Landing, perhaps at the refractories or Deep Water Desal sites, and that an alternate brine outfall could also be relocated if needed.
The filing did not include any timelines, permitting milestones, cost estimates or any other details originally requested by the judge.

ABSTRACT: Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, CALIFORNIA-AMERICAN WATER COMPANY CONTINGENCY PLAN COMPLIANCE FILING and Attachment 1 (1 of 4), Attachment 1 (2 of 4), Attachment 1 (3 of 4), Attachment 1 (4 of 4) and Attachment 2, are embedded. CONCLUSION Consistent with the Ruling, California American Water provides the Commission with reasonably detailed contingency plans for the proposed project. As previously discussed, California American Water stresses that these are simply contingency plans and believes that it has selected the appropriate project as part of its application. The Commission should not allow the intervening parties to use these contingency plans as a way to delay approval of the proposed project. Time is of the essence and California American Water asks the Commission to avoid any unnecessary delays to the proposed project’s completion.


Filing Date 11-01-12

Attachment 1 (1 of 4) 
TECHNICAL MEMORANDUM
Date: November 1, 2012
To: Richard Svindland, California American Water
From: Paul Findley, RBF Consulting
Subject: Contingency Planning for the Monterey Peninsula Water Supply Project

Attachment 1 (2 of 4) 
Monterey Peninsula Water Supply Project
Figures 1-7 - Proposed Intake System & Intake Contingency Options 1- 6

Attachment 1 (3 of 4) 
Monterey Peninsula Water Supply Project
Figures 8 - 9 - Intake Contingency Options 7 & 8; Figures 10 – 13 Discharge Contingency Options 1-4; Figure 14 - Desalination Plant Site Contingency Option 1
  
Attachment 1 (4 of 4) 
Figures 15 - 21 - Desalination Plant Site Contingency Options 2 - 8

Attachment 2
Monterey Peninsula Water Management District

Proceeding Number A.12-04-019 CALIFORNIA-AMERICAN WATER COMPANY COMPLIANCE PROGRESS REPORT FILING

RELATED NEWS ARTICLE: 
Cal Am files opposition with PUC to public ownership of desal plant 
Company tells PUC it could consider sharing oversight
By JIM JOHNSON Herald Staff Writer, 11/10/2012

EXCERPT HIGHLIGHTS:
Cal Am acknowledged that it had previously expressed support for some of the "concepts" in the authority's proposal, but said it wouldn't support any such proposal unless and until the authority ceased actively backing any alternative project.
Cal Am also made it clear it would seek permission from the PUC and the state water board before agreeing to any public participation proposal, and included in its filing a version of the authority's proposal that included a series of suggested changes.
Next up for the Cal Am water project proceeding, the PUC will conduct a project cost workshop Dec. 11-13, and a pre-hearing conference on Dec. 13 at the commission headquarters in San Francisco.


ABSTRACT: Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, CALIFORNIA-AMERICAN WATER COMPANY COMPLIANCE PROGRESS REPORT FILING, is embedded. "The Monterey Peninsula Regional Water Authority and County of Monterey (“Regional Water Authority”); Monterey Peninsula Water Management District (“MPWMD”); the City of Pacific Grove (“City”); and the City and Moss Landing Commercial Park, LLC (referred to as the “People’s Project”), each submitted on October 1, 2012 a proposal for direct public agency participation in the Monterey Peninsula Water Supply Project (“MPWSP”). Consistent with the assigned Administrative Law Judge’s (“ALJ”) directive, California American Water reports on its efforts to consider “any public agency proposal for participation in the Monterey Peninsula Water Supply Project (MPWSP) that is feasible and sufficiently developed to allow implementation in a timely manner and that is made by October 1, 2012.” California American Water has met with the respective agencies to discuss their proposals and provides its responses below." Notably, with regard to MONTEREY PENINSULA REGIONAL WATER AUTHORITY AND COUNTY OF MONTEREY PROPOSAL, “California American Water appreciates the cooperative nature of the Regional Water Authority’s proposal, but it cannot support public ownership for the desalination component of the MPWSP.”

CALIFORNIA-AMERICAN WATER COMPANY COMPLIANCE PROGRESS REPORT FILING 10-26-12
Filing Date 10-26-12

Friday, November 02, 2012

Proceeding Number A.12-04-019 Public Utility Commissioners MICHAEL R. PEEVEY, TIMOTHY ALAN SIMON, MICHEL PETER FLORIO, CATHERINE J.K. SANDOVAL & MARK J. FERRON: DECISION DECLARING PREEMPTION OF COUNTY ORDINANCE AND THE EXERCISE OF PARAMOUNT JURISDICTION

ABSTRACT: On October 25, 2012, California Public Utility Commissioners MICHAEL R. PEEVEY, President, TIMOTHY ALAN SIMON, MICHEL PETER FLORIO, CATHERINE J.K. SANDOVAL and MARK J. FERRON unanimously concurred in the DECISION DECLARING PREEMPTION OF COUNTY ORDINANCE AND THE EXERCISE OF PARAMOUNT JURISDICTION. Summary states: This decision determines that the authority of the Commission in regard to this application preempts Monterey County Code of Ordinance, Title 10, Chapter 10.72, concerning the construction, operation and ownership of desalination plants. This decision further determines that the findings, conclusions and orders herein are an exercise of jurisdiction that is paramount to that of a county Superior Court concerning the same subject. The DECISION is embedded; the ORDER is reproduced.
DECISION DECLARING PREEMPTION OF COUNTY ORDINANCE AND THE EXERCISE OF PARAMOUNT JURISDICTION


 DECISION DECLARING PREEMPTION OF COUNTY ORDINANCE AND THE EXERCISE OF PARAMOUNT JURISDICTION 

O R D E R

IT IS ORDERED that:

1. The Commission’s authority, exercised through General Order 103-A in Application 12-04-019, preempts the Monterey County Desalination Ordinance, Title 10, Chapter 10.72.

2. Under § 1759 of the Pub. Util. Code, the Superior Court of San Francisco County in County of Monterey vs. California-American Water Company, Case No. CGC-12-521875, has no “jurisdiction to review, reverse, correct, or annul” the instant decision of the Commission or “to suspend or delay the execution or operation” of it.

3. The Commission shall not delay the instant proceeding to await developments in or the outcome of County of Monterey vs. California-American Water Company, Case No. CGC-12-521875, pending in the Superior Court of San Francisco County.

4. California-American Water Company is directed to seek expeditiously a dismissal, summary judgment or other favorable disposition in County of Monterey vs. California-American Water Company, Case No. CGC-12-521875, pending before the Superior Court of San Francisco County, on the ground that applicable law requires a determination that the Commission’s authority regarding Application 12-04-019 preempts the Monterey County Desalination Ordinance.

5. Preemption of Monterey County Desalination Ordinance, Title 10, Chapter 10.72 by Commission authority shall not prevent the Commission or California-American Water Company from taking into account related concerns and interests of the County of Monterey and from cooperating with the County of Monterey in regards to the Monterey Peninsula Water Supply Project proposed in Application 12-04-019.

6. Application 12-04-019 remains open.

This order is effective today.

Dated October 25, 2012, at Irvine, California.

ADDENDUM:
Public Results of Commission Meeting October 25, 2012 -- Agenda 3303
Item # 17