Notice to all Parties California American Water Co. Application A.12-04-019: Monterey Peninsula Water Supply Project (MPWSP) MPWSP EIR/EIS Schedule

ABSTRACT: On March 14, 2016, CalAm submitted an amended application with a revised project description which will be included in the draft EIR/EIS. The coordinated EIR/Environmental Impact Study (EIS) and amended application, among other events, have led to a revised schedule, as set forth below. These dates are subject to change in the event of unforeseen circumstances,” according to the Notice.
REVISED SCHEDULE
Task
Completion Date

Preparation of the draft EIR/EIS
-----------------------------------
Draft EIR/EIS Issued for Public Comment
December 21, 2016
End of the 45 day Public Review/Comment
Period
February 4, 2017

Final EIR/EIS Distributed
September 25, 2017
30 Day Review Federal Review Period
October 25, 2017
EIR/EIS Certification plus Notice Of
Determination and Record Of Decision
November 8, 2017

 The Notice to all Parties document copy is embedded. 
Notice to all Parties
California American Water Co. Application A.12-04-019: Monterey
Peninsula Water Supply Project (MPWSP)
MPWSP EIR/EIS Schedule

REFERENCES:  STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION
(Application A.12-04-019, filed April 23, 2012)

Desal project faces another delay, could result in water rationing
By Jim Johnson, Monterey Herald