REVISED
SCHEDULE
Task
|
Completion Date
|
Preparation of the draft EIR/EIS
|
-----------------------------------
|
Draft EIR/EIS Issued for Public
Comment
|
December 21, 2016
|
End of the 45 day Public
Review/Comment
Period
|
February 4, 2017
|
Final EIR/EIS Distributed
|
September 25, 2017
|
30 Day Review Federal Review
Period
|
October 25, 2017
|
EIR/EIS Certification plus Notice
Of
Determination and Record Of
Decision
|
November 8, 2017
|
The Notice to all Parties document copy is embedded.
Notice to all Parties
California American Water Co. Application A.12-04-019: Monterey
Peninsula Water Supply Project (MPWSP)
MPWSP EIR/EIS Schedule
California American Water Co. Application A.12-04-019: Monterey
Peninsula Water Supply Project (MPWSP)
MPWSP EIR/EIS Schedule