Proceeding Number A.12-04-019 E-MAIL RULING REVISING SCHEDULE FOR COMMENTS ON DRAFT ENVIRONMENTAL IMPACT REPORT

ABSTRACT: Re: Application of California-American Water Company (U210W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, the E-MAIL RULING REVISING SCHEDULE FOR COMMENTS ON DRAFT ENVIRONMENTAL IMPACT REPORT document copy is embedded. IT IS RULED that comments on the Draft Environmental Impact Report are due July 1, 2015.
Filing Date 6-16-15
E-MAIL RULING REVISING SCHEDULE FOR COMMENTS ON DRAFT ENVIRONMENTAL IMPACT REPORT