ABSTRACT: Re: Application of California-American Water Company (U210W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, the SECOND AMENDED SCOPING MEMO AND RULING OF THE ASSIGNED COMMISSIONER document copy is embedded. Summary This Second Amended Scoping Memo and Ruling of the assigned Commissioner extends the statutory deadline in this proceeding to December 31, 2016. Therefore, pursuant to Public Utilities Code Section 1701.5(b), an extension to December 31, 2016 for completion of this proceeding will permit reasonable time to complete environmental work, GWR Phase II, the Commission decision assessing CPCN (Certificate of Public Convenience and Necessity) issues (Phase I and Phase II) and environmental issues, and other possible contingencies. IT IS RULED that the statutory deadline for this proceeding is December 31, 2016.
SECOND AMENDED SCOPING MEMO AND RULING OF THE ASSIGNED COMMISSIONER