ABSTRACT: Re: In the Matter of the Application of California American Water Company (U 210 W) for Approval of the Monterey Peninsula Water Supply Project and Authorization to Recover All Present and Future Costs in Rates, ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE document is embedded. Gary Weatherford, Administrative Law Judge, ruled on January 23, 2015, as follows:
Accordingly, the schedule is modified to be as follows:
April 2015 – DEIR issued for comment.
60 days from DEIR – Comments on DEIR.
75 days from DEIR – Opening Briefs filed and served.
15 days from Opening Briefs – Reply Briefs filed and served.
July 2015 – All-party meeting.
October 2015 – FEIR published.
December 2015 – Proposed Decision issued.
January 2016 – All-party meeting.
February 2016 – Proposed Decision on Commission Agenda.
IT IS RULED that:
1.The schedule for this proceeding is modified as described above.
2. Ex parte communications with decision makers in this proceeding are prohibited.
Filing Date 1-23-15
ADMINISTRATIVE LAW JUDGE’S RULING UPDATING SCHEDULE
REFERENCE:
CPUC judge delays Peninsula desal project EIR again
By Jim Johnson, Monterey Herald