Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All
labor and materials related to the following: Reference PCO #64 (Otto's tracking
number), Bulletin #26 R1. Summary of Work; Revisions to Handrail Extensions.
Agreed Lump Sum $5,105.00
2 CONTRACT PRICE
Total increase
in contract price $5,105.00
3 CONTRACT TIME
Eight (8)
additional working days for this CCO
No (0)
additional weather days for this CCO
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,551,672.00
Accepted Date
1/27/2016
City of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 26
No comments: