1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Provide
all labor and materials related to the following: Reference RFP #35 and PCO #54 (Otto's
tracking number). Summary of Work; caulk
joints when installing
new plywood stage decking.
Agreed
Lump Sum $ 2,096.00
2 CONTRACT PRICE
Total
increase in contract price $2,096.00
3 CONTRACT TIME
One
(1) additional working day for this CCO
Add
one (1) weather day for 12-10-15
NOTE: CLERICAL
ERRORS IN PRIOR CCO'S RESULTED IN AN INCORRECT NUMBER OF TIME EXTENSION DAYS UP
TROUGH CCO 18. THIS CCO AMENDS PRIOR ERRORS. THE TOTAL NUMBER OF TIME EXENSION
DAYS IS HEREBY CORRECTED TO 49.
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,549,653.00
Accepted Date 1/13/2016
City