FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 19

Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Provide all labor and materials related to the following: Reference RFP #35 and PCO #54 (Otto's tracking number). Summary of Work; caulk joints when installing new plywood stage decking.
Agreed Lump Sum $ 2,096.00

2 CONTRACT PRICE
Total increase in contract price $2,096.00

3 CONTRACT TIME
One (1) additional working day for this CCO
Add one (1) weather day for 12-10-15
NOTE: CLERICAL ERRORS IN PRIOR CCO'S RESULTED IN AN INCORRECT NUMBER OF TIME EXTENSION DAYS UP TROUGH CCO 18. THIS CCO AMENDS PRIOR ERRORS. THE TOTAL NUMBER OF TIME EXENSION DAYS IS HEREBY CORRECTED TO 49.

Original Contract Price $1,462,236.00
Revised Contract Price: $1,549,653.00

Accepted Date 1/13/2016
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 19