Sunday, February 28, 2016

FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 22

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Deletion: Credit all labor and materials related to the following: Reference PCO #70 (Otto's tracking number). Summary of Work; Delete furnishing and installing fifteen (15) 24" boxed trees.
Agreed Lump Sum $ (9,000.00)

2 CONTRACT PRICE
Total decrease in contract price $(9,000.00)

3 CONTRACT TIME
No (0) additional working days for this CCO
Seven (7) additional weather days for this CCO
Weather days: 1/4/16, 1/5/16, 1/6/16. 1/7/16, 1/8/16, 1/13/16, 1/18/16

Original Contract Price $1,462,236.00
Revised Contract Price: $1,542,420.00

Accepted Date 1/27/2016
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 22

No comments: