Description
CHANGES TO CONTRACT PLANS AND
SPECIFICATIONS.
Deletion:
Credit all labor and materials related to the
following: Reference PCO #70 (Otto's tracking number). Summary of Work; Delete furnishing and
installing fifteen (15) 24" boxed trees.
Agreed
Lump Sum $ (9,000.00)
2 CONTRACT PRICE
Total
decrease in contract price $(9,000.00)
3 CONTRACT TIME
No
(0) additional working days for this CCO
Seven (7) additional weather days
for this CCO
Weather
days: 1/4/16, 1/5/16, 1/6/16. 1/7/16, 1/8/16, 1/13/16, 1/18/16
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,542,420.00
Accepted Date 1/27/2016
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 22
No comments: