FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 14

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFP
#23r1 , Bulletin #8 (revised), and PCO #40 (Otto's tracking number). Summary of Work;
reconfigure floor plan for dressing rooms from two small dressing rooms to one large dressing
room and add electrical outlets, and other electrical. Changes made as requested by user
groups.
Agreed Lump Sum $ 4,992.00

2 CONTRACT PRICE
Total Increase in contract price $ 4,992.00

3 CONTRACT TIME
One weather day added for the following date: 11-2-15

Original Contract Price $1,462,236.00
Revised Contract Price: $1,540,959.00

Accepted Date 11/11/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 14