FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 15

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFI
#18 and PCO #7rev1 (Otto's tracking number). Summary of Work; Construct new retaining wall with stone veneer.
Agreed Lump Sum $ 7,589.00

2 CONTRACT PRICE
Total Increase in contract price $ 7,589.00

3 CONTRACT TIME
Weather day for 11-9-15

Original Contract Price $1,462,236.00
Revised Contract Price: $1,548,548.00

Accepted Date 11/18/2015