Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFI
#18 and PCO
#7rev1 (Otto's tracking number). Summary of Work; Construct new retaining wall with
stone veneer.
Agreed Lump Sum
$ 7,589.00
2 CONTRACT PRICE
Total Increase
in contract price $ 7,589.00
3 CONTRACT TIME
Weather
day for 11-9-15
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,548,548.00
Accepted Date 11/18/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 15