FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 18

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Deletion: Credit labor and materials related to the following: Reference RFP #25, Bulletins #14
& 14.1, and PCO #42 Rev1 (Otto's tracking number). Summary of Work; multiple items related to "Driveway Revisions" and difficulty in drilling driveway piers.
Agreed Lump Sum $ (12,203.00)

2 CONTRACT PRICE
Total decrease in contract price $ (12,203.00)

3 CONTRACT TIME
Twenty Five (25) additional working days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,547,557.00
Accepted Date 12/9/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 18