CHANGES TO CONTRACT PLANS AND
SPECIFICATIONS.
Deletion:
Credit labor and materials related to the following: Reference RFP #25, Bulletins #14
&
14.1, and PCO #42 Rev1 (Otto's tracking number). Summary
of Work; multiple items related to "Driveway Revisions" and
difficulty in drilling driveway piers.
Agreed
Lump Sum $ (12,203.00)
2 CONTRACT PRICE
Total
decrease in contract price $ (12,203.00)
3 CONTRACT TIME
Twenty Five (25) additional working days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,547,557.00
Accepted Date 12/9/2015
City