FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 10

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFI #9 and PCO #19 (Otto's tracking number). Summary of Work includes installing utility and irrigations sleeves at various locations throughout the site.
Agreed Lump Sum $12,472.00

2 CONTRACT PRICE
Total Increase in contract price $12,472.00

3 CONTRACT TIME
Two additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,522,407.00

Accepted Date 10/13/2015