FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 13

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
RFP #11, RFI #14R1 , and PCO #27 (Otto's tracking number). Summary of Work; in lieu of excavating between seating rows, grade and pour on native and install dowling into concrete seat pedestals.
Agreed Lump Sum $ (362.00)
2 CONTRACT PRICE
Total Increase in contract price $ (362.00)

3 CONTRACT TIME
Three days less

Original Contract Price $1,462,236.00
Revised Contract Price: $1,535,967.00

Accepted Date 11/11/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 13