CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
#8, PCO #25
(Otto's tracking number). Summary of Work includes laying out with marking paint
the as-permitted accessible parking stall, as well as a proposed reconfigured
accessible parking stall as directed by City Council. Layout was used to show
an assembly of Council, staff, and the public attending a site meeting prior to
Council meeting to discuss the potential reconfiguration.
Agreed Lump Sum
$593.00
2 CONTRACT PRICE
Total Increase
in contract price $ 593.00
3 CONTRACT TIME
No additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,495,096.00
Accepted Date 9/9/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 5