ABSTRACT:
The “staff now anticipates a Substantially Complete date of March 31,
2016,” according to the AGENDA BILL, Forest Theater Renovation Project Update, March 1, 2016
Consent Calendar.
CONTRACT CHANGE ORDERS for the FOREST THEATER RENOVATION PROJECT
are presented; there are twenty-six (26) CONTRACT CHANGE ORDERS as of February
2016. CONTRACT CHANGE ORDERS NOS. 1-26
document copies are embedded; Descriptions reproduced
NOTES: Revised
Contract Price: $1,551,672.00 (as of CONTRACT CHANGE ORDER NO. 26) Accepted
Date 1/27/2016; Original Contract Price $1,462,236.00
Council awarded
a 10% construction contingency in the amount of $146,224.00; $167,570.00 is the
adjusted total amount of all change orders which the City Administrator has
authority to sign, or 11.46% of the Original Contract Price.
No comments:
Post a Comment