Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All
labor and materials related to the following: Reference PCO #67 (Otto's tracking
number), RFI #71 , and RFP #22. Summary of Work; Raise fire sprinkler line to
avoid interference with new footing.
Agreed Lump Sum
$1,784.00
2 CONTRACT PRICE
Total increase
in contract price $1,784.00
3 CONTRACT TIME
No (0)
additional working days for this CCO
No
(O) additional weather days for this CCO
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,546,114.00
Accepted Date 1/27/2016