FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 24

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All labor and materials related to the following: Reference PCO #67 (Otto's tracking number), RFI #71 , and RFP #22. Summary of Work; Raise fire sprinkler line to avoid interference with new footing.
Agreed Lump Sum $1,784.00

2 CONTRACT PRICE
Total increase in contract price $1,784.00

3 CONTRACT TIME
No (0) additional working days for this CCO
No (O) additional weather days for this CCO

Original Contract Price $1,462,236.00
Revised Contract Price: $1,546,114.00

Accepted Date 1/27/2016
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 24