FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 23

Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All labor and materials related to the following: Reference PCO #62 (Otto’s tracking number) and Bulletin 23 R1.  Summary of Work; Add secondary footing to south retaining wall adjacent to parking stall.
Agreed Lump Sum $1,910.00

2 CONTRACT PRICE
Total decrease in contract price $1,910.00

3 CONTRACT TIME
No (0) additional working days for this CCO
No (0) additional weather days for this CCO

Original Contract Price $1,462,236.00
Revised Contract Price: $1,544,330.00

Accepted Date 1/27/2016
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 23