Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition:
All labor and materials related to the following: Reference PCO #62 (Otto’s
tracking number) and Bulletin 23 R1.
Summary of Work; Add secondary footing to south retaining wall adjacent
to parking stall.
Agreed
Lump Sum $1,910.00
2 CONTRACT PRICE
Total
decrease in contract price $1,910.00
3 CONTRACT TIME
No
(0) additional working days for this CCO
No
(0) additional weather days for this CCO
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,544,330.00
Accepted Date 1/27/2016