Description
CHANGES TO CONTRACT PLANS AND
SPECIFICATIONS.
Addition:
Provide all labor and materials related to the following: Reference
PCO #57 (Otto's tracking number). Summary
of Work; PIER DRILLING EXTRA WORK
Agreed
Lump Sum $ 510.00
2 CONTRACT PRICE
Total
increase in contract price $ 510.00
3 CONTRACT TIME
No
(0) additional working days for this CCO
No
(0) additional weather days for this CCO
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,550,163.00
Accepted Date 1/13/2016
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 20