FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 8

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFI #32 and PCO #17 (Otto's tracking number). Summary of Work includes trace existing conductors/conduits at east pathway and abandon, pull wires, remove conduit, etc.
Agreed Lump Sum $ 6,060.00

2 CONTRACT PRICE
Total Increase in contract price $ 6,060.00

3 CONTRACT TIME
No additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,503,723.00

Accepted Date 10/13/2015