Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFI #32
and PCO #17 (Otto's tracking number). Summary of Work includes trace existing conductors/conduits
at east pathway and abandon, pull wires, remove conduit, etc.
Agreed
Lump Sum $ 6,060.00
2 CONTRACT PRICE
Total
Increase in contract price $ 6,060.00
3 CONTRACT TIME
No additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,503,723.00
Accepted Date 10/13/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 8