Description:
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS
Request for
Proposal #3 by the City of Carmel-By-The-Sea and in relation to RFI #16. Adjust
new wood deck to
correct elevation. Provide new handrails for new ramp slope of 1:12. Modify
furnace door,
provide new built up curb (wood), remove and fill existing vents and cut new vents
at deck level.
Agreed Lump Sum
$4,898.00
2 CONTRACT PRICE
Total Increase
in contract price $4,898.00
3 CONTRACT TIME
No additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,467,134.00
Accepted Date
10/13/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 1