FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 1

Description:
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS
Request for Proposal #3 by the City of Carmel-By-The-Sea and in relation to RFI #16. Adjust
new wood deck to correct elevation. Provide new handrails for new ramp slope of 1:12. Modify
furnace door, provide new built up curb (wood), remove and fill existing vents and cut new vents at deck level.
Agreed Lump Sum $4,898.00

2 CONTRACT PRICE
Total Increase in contract price $4,898.00

3 CONTRACT TIME
No additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,467,134.00

Accepted Date 10/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 1