1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All
labor and materials related to the following: Reference PCO
#15 (Otto's tracking number), RFI #29. Summary of Work; Relocate
existing hose bib and electrical conduit.
Agreed
Lump Sum $453.00
2 CONTRACT PRICE
Total
increase in contract price $453.00
3 CONTRACT TIME
No
(0) additional working days for this CCO
No (0) additional weather
days for this CCO
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,546,567.00
Accepted Date
1/27/2016