FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 25

Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: All labor and materials related to the following: Reference PCO #15 (Otto's tracking number), RFI #29. Summary of Work; Relocate existing hose bib and electrical conduit.
Agreed Lump Sum $453.00

2 CONTRACT PRICE
Total increase in contract price $453.00

3 CONTRACT TIME
No (0) additional working days for this CCO
No (0) additional weather days for this CCO

Original Contract Price $1,462,236.00
Revised Contract Price: $1,546,567.00

Accepted Date 1/27/2016
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 25