FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 2

Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference Request for Information #25 by the City of Carmel-By-The-Sea and Otto's PCO #13 (their tracking number, not City's). Work includes demolition of existing concrete curbs, excavation of soil to 5" below existing finished concrete floor, compaction of subgrade, concrete, rebar, dowels, relocation of existing water lines (per RFI #25) and wood box curb. Excludes inspections, engineering and testing fees.
Agreed Lump Sum $4,638.00

2 CONTRACT PRICE
Total Increase in contract price $4,638.00

3 CONTRACT TIME
No additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,471,772.00

Accepted Date 10/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 2