FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 16

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFP #24, Bulletins 16, 16.1, and 16.2, and PC0#41 rev1 (Otto's tracking number). Summary of Work; Electrical Closest Revisions
Agreed Lump Sum $ 14,230.00

2 CONTRACT PRICE
Total Increase in contract price $ 14,230.00

3 CONTRACT TIME
Three (3) days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,562,778.00

Accepted Date 11/18/2015