FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 3

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference
Bulletin #13, RFP #20, and PCO #38 (Otto's tracking number). Work includes insulating
between the floor joist at the indoor theater stage.
Agreed Lump Sum $ 1,385.00

2 CONTRACT PRICE
Total Increase in contract price

3 CONTRACT TIME
No additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,473,157.00

Accepted Date 10/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 3