Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFP #6,
RFI #27 and PCO #14 (Otto's tracking number). Summary of Work includes removing
noncompliant/deficient drain leader-head and piping and installing new compliant
leader-head and piping.
Agreed Lump Sum
$1,362.00
2 CONTRACT PRICE
Total Increase
in contract price $1,362.00
3 CONTRACT TIME
No additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,523,769.00
Accepted Date 10/14/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 11