CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFP #10,
RFI #20 and PCO #9 (Otto's tracking number). Summary of Work includes removing four
niches from stage perimeter.
Agreed Lump Sum
$12,560.00
2 CONTRACT PRICE
Total Increase
in contract price $12,560.00
3 CONTRACT TIME
Two
additional days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,536,329.00
Accepted Date
10/8/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 12