FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 12

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFP #10, RFI #20 and PCO #9 (Otto's tracking number). Summary of Work includes removing four niches from stage perimeter.
Agreed Lump Sum $12,560.00

2 CONTRACT PRICE
Total Increase in contract price $12,560.00

3 CONTRACT TIME
Two additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,536,329.00

Accepted Date 10/8/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 12