FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 9

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
#14, RFI #34 and PCO #19 (Otto's tracking number). Summary of Work includes remove existing corners of the main stage, partially demo existing stone wall and install new concrete sill, new framing and new T111 siding to match existing
Agreed Lump Sum $6,212.00
2 CONTRACT PRICE
Total Increase in contract price $6,212.00
3 CONTRACT TIME
Two additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,509,935.00

Accepted Date 10/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 9