Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
#14, RFI #34 and
PCO #19 (Otto's tracking number). Summary of Work includes remove existing
corners of the main stage, partially demo existing stone wall and install new concrete
sill, new framing and new T111 siding to match existing
Agreed Lump Sum
$6,212.00
2 CONTRACT PRICE
Total Increase
in contract price $6,212.00
3 CONTRACT TIME
Two additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,509,935.00
Accepted Date 10/13/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 9
No comments: