Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFI
#14, RFP #1 ,
and PCO #1 Rev #2 (Otto's tracking number). Summary of Work includes changing
the step layout to the "Terraced Step" design; deleting the sub-excavation
between rows and instead doweling into bench pedestals between rows, slope
grading and pour between rows, drainage system between rows, etc.
Agreed Lump Sum $21,346.00
2 CONTRACT PRICE
Total Increase
in contract price 21,346.00
3 CONTRACT TIME
Sixteen
additional days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,494,503.00
Accepted Date
10/8/2015
Note to
Contracts and Budgets Office: Council awarded a 10% construction contingency in
the amount of $146,224.00 and the cost of "Terraced Step" design at a
Not to Exceed amount of $45,000.00 (actual cost@ $21,346.00). Thus $167,570.00
is the adjusted total amount of all change orders which the City Administrator
has authority to sign, or 11.46% of the Original Contract Price.
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 4
No comments: