Description
1 CHANGES TO
CONTRACT PLANS AND SPECIFICATIONS.
Addition:
Provide all labor and materials related to the following: Reference PCO #58 (Otto's
tracking number). Summary of Work; At asphalt & wood siding abutement add
metal flashing at wood siding and add layer of additional siding. Caulk as
needed.
Agreed Lump Sum
$1,257.00
2 CONTRACT PRICE
Total increase
in contract price $1,257.00
3
CONTRACT TIME
No
(0) addition working days for this CCO
Five
(5) additional weather days for this CCO
Weather
days: 12/11/15, 12/21/15. 12/22/15. 12/23/15, 12/28/15
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,551,420.00
Accepted Date 1/13/2015
City of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 21