FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 21

 Description
1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Provide all labor and materials related to the following: Reference PCO #58 (Otto's tracking number). Summary of Work; At asphalt & wood siding abutement add metal flashing at wood siding and add layer of additional siding. Caulk as needed.
Agreed Lump Sum $1,257.00

2 CONTRACT PRICE
Total increase in contract price $1,257.00

3 CONTRACT TIME
No (0) addition working days for this CCO
Five (5) additional weather days for this CCO
Weather days: 12/11/15, 12/21/15. 12/22/15. 12/23/15, 12/28/15

Original Contract Price $1,462,236.00
Revised Contract Price: $1,551,420.00

Accepted Date 1/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 21