FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 17

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Deletion: Credit all labor and materials necessary related to the following: Reference RFP #7,
RFI #33 (partial) + RFI #38, and PC0#24rev1 (Otto's tracking number). Summary of Work; Delete lowering of existing conduit which crossed east path as bid.
Agreed Lump Sum $ (3,018.00)

2 CONTRACT PRICE
Total decrease in contract price $ (3,018.00)

3 CONTRACT TIME
None

Original Contract Price $1,462,236.00
Revised Contract Price: $1,559,760.00

Accepted Date 12/9/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 17