Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference RFI #47 and
PCO #44 (Otto's tracking number). Summary of Work includes removal of existing dry
roll sill plate and fasten new pressure treated studs to existing studs.
Agreed
Lump Sum $$ 602.00
2 CONTRACT PRICE
Total
Increase in contract price $ 602.00
3 CONTRACT TIME
No additional
days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,497,663.00
Accepted Date 10/13/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 7