FOREST THEATER RENOVATION PROJECT: CONTRACT CHANGE ORDER NO. 7

Description
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply all labor and materials necessary to complete the following: Reference RFI #47 and PCO #44 (Otto's tracking number). Summary of Work includes removal of existing dry roll sill plate and fasten new pressure treated studs to existing studs.
Agreed Lump Sum $$ 602.00

2 CONTRACT PRICE
Total Increase in contract price $ 602.00

3 CONTRACT TIME
No additional days

Original Contract Price $1,462,236.00
Revised Contract Price: $1,497,663.00

Accepted Date 10/13/2015
City of Carmel-by-the-Sea
PUBLIC WORKS DEPARTMENT
CONTRACT CHANGE ORDER NO. 7