CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.
Addition: Supply
all labor and materials necessary to complete the following: Reference PCO #43
(Otto's tracking number). Summary of Work includes hydro jetting of both
6" and 4" storm line removing dirt/root build-up/debris. Ran jetter
upstream and downstream to exit point 3-4 times. Cleared out catch basins
shoveling out dirt/debris.
Agreed Lump Sum.
$1,965.00
2 CONTRACT PRICE
Total Increase
in contract price 1,965.00
3 CONTRACT TIME
No
additional days
Original
Contract Price $1,462,236.00
Revised Contract
Price: $1,497,061.00
Accepted Date 10/12/2015
City
of Carmel-by-the-Sea
PUBLIC
WORKS DEPARTMENT
CONTRACT
CHANGE ORDER NO. 6